1. After the color steel plate enters the site, it should be kept away from the fire source. When stored in the open air, non-combustible materials should be used to completely cover the color steel plate.
2. For the sandwich color steel plate that needs to take fireproof structural measures, the construction of the fireproof isolation belt should be carried out simultaneously with the construction of the thermal insulation color steel plate.
3. The construction of flammable and flame-retardant sandwich color steel plates should be carried out in sections.
4. For the supporting members of the curtain wall and the supporting members of the air conditioner and other facilities, the electric welding and other processes should be carried out before the color steel plate is laid. If it really needs to be carried out after the color steel plate is laid, fire protection measures such as fire blankets should be laid around and at the bottom of the electric welding part.
5. The hot-melt and hot-bond construction of waterproof materials shall not be carried out directly on the color steel plate.
6. Reliable fire protection measures should be taken when high temperature equipment such as construction lighting is close to the combustible sandwich color steel plate.
7. The high temperature environment should be avoided when the sandwich color steel plate such as polyurethane is foamed on site. Anti-static measures should be taken for construction technology, tools and clothing.
8. Indoor and outdoor temporary fire hydrant systems should be set up at the construction site, and meet the fire water supply requirements for fire fighting at the construction site.
9. The construction work station of the external thermal insulation project should be equipped with sufficient fire extinguishing equipment. In order to ensure the overall construction safety.